Remodeling change orders: what to record before approving extra work

By ContractorsNow · Published

Use a written change order to record what changes, why it changes, the price difference and the effect on the schedule. Follow the approval process in your agreement before additional work proceeds. If an urgent condition needs immediate attention, ask the contractor to separate temporary protection from the proposed permanent repair.

First decide what kind of change you are discussing

Changes often start with a casual conversation. You choose a different tile, a cabinet arrives in the wrong size or demolition reveals a condition nobody could see earlier. Ask whether the issue is a new homeowner request, a hidden condition, a product problem or work already covered by the original scope. That distinction helps you ask the right questions without guessing who owes what.

Find the relevant line in your agreement. If the original scope already includes the work being discussed, ask why a new charge is proposed. If it excludes the condition, ask for a description and any photos or assessment supporting the proposed repair. A visible problem does not by itself explain the entire recommended scope.

Change-order review worksheet
RecordWhat to ask
ReferenceWhich proposal version and original line does this change?
ReasonRequested upgrade, hidden condition or another cause?
Revised workWhat is added, removed or replaced?
PriceAdded labor/materials, credits and any agreed markup?
TimingWhich milestone changes, and what does it depend on?
ApprovalWho can approve, and what records confirm approval?

Ask for the whole price difference

A replacement product can create several adjustments. Ask for a credit for any omitted item, the new item cost, installation differences and other affected work. A countertop change, for example, may involve edge details, fabrication, a sink cutout or a delivery change. Compare the complete revision with the original scope.

Use a running total. Start with the agreed contract amount, list each approved addition and credit, and show the revised amount. Keep a proposed change separate from an approved change. Otherwise an email estimate can become part of the budget before you have agreed to it.

Make the schedule consequence specific

Ask which activity is affected and what must happen before work resumes. A revised completion date is more useful when you know whether it depends on a product delivery, an inspection or a new design decision. Record any temporary arrangement needed to keep the household functioning.

Use the communication channel and authorized decision maker named in your agreement. When several family members speak with different crew members, a simple approval log avoids confusion. Put the date, revision number and approver on the same record as the scope and price.

Handle urgent discoveries carefully

If a contractor reports an immediate safety or water concern, ask them to explain the urgency and the temporary steps they recommend. Do not use a planning worksheet to delay a needed emergency response. Separate the immediate protection decision from a larger permanent scope, and consult the appropriate qualified professional when the condition requires it.

Keep closeout tied to the current agreement

At the end of the job, compare the completed work with the original scope plus approved changes. Keep unresolved questions, warranty documents and the agreed payment milestones together. The FTC advises homeowners to read their contract carefully and check applicable local requirements. This worksheet organizes your conversation; it does not determine legal responsibility.

Use our proposal comparison guide before choosing a contractor, and our whole-home planning guide to agree on communication before work starts.

Sources and editorial notes

Sources checked October 11, 2026. This guide combines attributed source facts with original planning worksheets. It is general information, not an inspection, local estimate or professional determination. Costs and requirements depend on your property and location.